Tillicum & Lampson active transportation improvement project

Share Tillicum & Lampson active transportation improvement project on Facebook Share Tillicum & Lampson active transportation improvement project on Twitter Share Tillicum & Lampson active transportation improvement project on Linkedin Email Tillicum & Lampson active transportation improvement project link
active transportation improvement project

About this project

The township has proposed design improvements for both Lampson and Tillicum streets. Using feedback based on our Active Transportation Network Plan public engagement as well as previous surveys, these draft designs aim to enhance road safety for cyclists and pedestrians.

Plan highlights include protected bike lanes on Tillicum Road from Gorge to Craigflower with further connections to Lampson southbound on Tillicum and east/west on Craigflower. Lampson Street will include protected bike lanes from Esquimalt Road to Transfer Street and a short section of neighbourhood bikeways on Lampson between Craigflower and Transfer. There will also be new crossings added along both corridors and the removal of an aging/redundant traffic signal at Head Street and Old Esquimalt Road.

Project update

Project construction begins in August 2023.

More information

  • Council meeting and staff report to Esquimalt Committee of the Whole on January 16, 2023
  • Read the public engagement summary "What we heard" Report: December 2022
  • Both Lampson Street and Tillicum Road—which see 11,350 and 17,000 daily vehicles respectively—have gaps in both the cycling and pedestrian networks. The corridors provide key north-south travel routes through the township.
  • Keeping regional transportation in mind, the planned infrastructure connects to the District of Saanich’s recently added bike lanes on the north side of the Gorge Bridge on Tillicum Road. The planned improvements will connect the two communities to allow for continuous protected cycling along the major routes.
  • The township is taking a “quick build” approach to the designs: quick-build facilities allow for faster construction times while still delivering all Ages and Abilities (AAA) bike facilities. Quick-build facilities also tend to be more economical to install and allow the township to focus funds on other upgrades including roadway surface and intersection/crossing improvements.
  • Parking will be removed in two areas: Esquimalt to Old Esquimalt = ~17 spaces and Old Esquimalt to Colville = ~24 spaces

About this project

The township has proposed design improvements for both Lampson and Tillicum streets. Using feedback based on our Active Transportation Network Plan public engagement as well as previous surveys, these draft designs aim to enhance road safety for cyclists and pedestrians.

Plan highlights include protected bike lanes on Tillicum Road from Gorge to Craigflower with further connections to Lampson southbound on Tillicum and east/west on Craigflower. Lampson Street will include protected bike lanes from Esquimalt Road to Transfer Street and a short section of neighbourhood bikeways on Lampson between Craigflower and Transfer. There will also be new crossings added along both corridors and the removal of an aging/redundant traffic signal at Head Street and Old Esquimalt Road.

Project update

Project construction begins in August 2023.

More information

  • Council meeting and staff report to Esquimalt Committee of the Whole on January 16, 2023
  • Read the public engagement summary "What we heard" Report: December 2022
  • Both Lampson Street and Tillicum Road—which see 11,350 and 17,000 daily vehicles respectively—have gaps in both the cycling and pedestrian networks. The corridors provide key north-south travel routes through the township.
  • Keeping regional transportation in mind, the planned infrastructure connects to the District of Saanich’s recently added bike lanes on the north side of the Gorge Bridge on Tillicum Road. The planned improvements will connect the two communities to allow for continuous protected cycling along the major routes.
  • The township is taking a “quick build” approach to the designs: quick-build facilities allow for faster construction times while still delivering all Ages and Abilities (AAA) bike facilities. Quick-build facilities also tend to be more economical to install and allow the township to focus funds on other upgrades including roadway surface and intersection/crossing improvements.
  • Parking will be removed in two areas: Esquimalt to Old Esquimalt = ~17 spaces and Old Esquimalt to Colville = ~24 spaces
  • CLOSED: This survey has concluded.

    Please take a short survey to comment on the specific design features. Feedback will be collected and shared with council in January 2023.


    Personal information contained in this survey is collected under Section 26 (c) of the Freedom of Information and Protection of Privacy Act and will be used only for the purposes of collecting feedback for the Lampson and Tillicum corridor project. If you have any questions about the collection or use of your personal information, please contact the Corporate Officer at corporate.services@esquimalt.ca or 250-414-7135.

    Having trouble with the tool? Contact us or pick one up during business hours at Esquimalt Municipal Hall after December 5.

     View the plans and street designs

    Share Survey: Changes to Lampson & Tillicum corridors on Facebook Share Survey: Changes to Lampson & Tillicum corridors on Twitter Share Survey: Changes to Lampson & Tillicum corridors on Linkedin Email Survey: Changes to Lampson & Tillicum corridors link
Page last updated: 09 Aug 2023, 12:05 PM